High Power Line Penela – “Vila Chã”, 400KV and “Vila Chã B” Subestation, 400/60 KV
TYPOLOGY
Environmental Impact Study of Very High Voltage Power Line and Substation
PHASE
Preliminary Study
Execution Project
LOCATION
Ansião, Figueiró dos Vinhos, Pedrógão Grande, Castanheira de Pera, Penela, Góis, Arganil, Tábua, Oliveira do Hospital, Santa Comba Dão, Tondela, Carregal do Sal, Nelas e Seia
CLIENT
ELECTROLINHAS,lda and REN, S.A.
DATE OF PROJECT
PS –February 2012 to August 2013
EP – August 2015
LENGTH
≈ 110 km
BRIEF DESCRIPTION
Power line and substation that allows the reinforcement of National Transport Network (RNT), to receive energy from the future hydroelectric Girabolhos and other alternative renewable energy projects, in particular wind power.
SINGULARITIES
– In the south, the line crosses a rugged terrain and a predominantly forest area, while in the north, an area more conditioned by the presence of populations